PROJECT OVERVIEW

Get an overview and learn more about roles and functions in a wide variety of projects.


2023

07/2023 - 10/2023

Active ingredient production |
Bulk filling with insulator

Project Type:
Target:
Role:
Budget:
Project Team:
Revamp, active ingredient production BioTech
Quality assurance, savings
Project engineer/process architect
On request
On request
Complexity: Medium

- Planning a conversion in the area of the bulk filling (isolator and lifting columns)
- Identification of required interfaces
- Estimation of conversion measures through inventory
- Creation of specifications
- Support for 3D collision planning
- Creation of a dismantling concept
- Technical support for the re-qualification of the cleanroom


2023

01/2023 - 12/2023

PROCESS OPTIMIZATION
Implementation of regulatory requirements

Project Type:
Target:
Role:
Budget:
Project Team:
Quality assurance, medical devices
Compliance with normative requirements
Project Manager
EUR 0.3 million
4 people
Complexity: Medium

- Planning and execution of tests in the area of process development & process design
- Preparation of specifications for system procurement
- Carrying out risk analyses (FMEA)
- Creation, updating and training of process, test and work instructions
- Execution and documentation of required validations / re-validations of processes & software
- Planning the implementation of physical product properties
- Qualification & validation of packaging, transport, washing and cleaning processes related to products.
- Qualification and validation of cleanrooms (ISO class 7/8 according to DIN EN 14644)
- Preparations for internal and external audits

2022

06/2022 - 12/2022

PROCESS OPTIMIZATION
Implementation of regulatory requirements

Project Type:
Target:
Role:
Budget:
Project Team:
Quality assurance, medical devices
Compliance with normative requirements
Project Manager
EUR 0.3 million
4 people
Complexity: Medium

- Planning and execution of tests in the area of process development & process design
- Preparation of specifications for system procurement
- Carrying out risk analyses (FMEA)
- Creation, updating and training of process, test and work instructions
- Execution and documentation of required validations / re-validations of processes & software
- Planning the implementation of physical product properties
- Qualification & validation of packaging, transport, washing and cleaning processes related to products.
- Qualification and validation of cleanrooms (ISO class 7/8 according to DIN EN 14644)
- Preparations for internal and external audits


2022

03/2019 - 02/2022

GLOBAL STANDARDIZATION | Hardening Processes

Project Type:
Target:
Role:
Budget:
Project Team:
Restructuring, Medical Devices
Standardization, cost saving
Project engineer, quality engineer
On request
On request
Complexity: Medium
- Standardization of the hardening process
- Comprehensive test planning
- Definition of the new hardening process & rollout
- Presentation of the project status
- Contact person for process validation
- Process optimization


2021

09/2019 - 02/2021

NEW CLEANROOM CONSTRUCTION | Complete planing

Project Type:
Target:
Role:
Budget:
Project Team:
New construction, Medical Devices
Expansion of production, securing of location
Project Manager
On request
On request
Complexity: Very high

- Project management from project start, design planning, detailed planning, construction supervision, acceptance & qualification
- Specifications for layouts and infrastructure planning
- Support with cost estimation
- Preparation of technical documents (URS)
- Internal and external interface coordination
- Responsible for the management of the qualification clean room & process plants
- Close cooperation with authorities
- Specifications for the validation of the washout processes
- Participation in risk analyses


2021

08/2019 - 08/2021

PRODUCTION TRANSFER | Existing production Line

Project Type:
Target:
Role:
Budget:
Project Team:
Production Transfer & Conversion, Medical Devices
Growth increase, cost savings
Project Manager (Cleanroom & nfrastructure)
On request
On request
Complexity: Medium - High

- Planning of the production transfer
- Comprehensive inventory and process improvement
- Layout planning
- Interface coordination
- Transfer of production processes
- Main contact person for qualification planning process plants & cleanrooms
- Preparation of risk analyses


2020

08/2019 - 11/2020

STANDARDIZATION | Final Cleaning Processes

Project Type:
Target:
Role:
Budget:
Project Team:
Restructuring
Sandardization, cost saving
Project Manager
On request
On request
Complexity: Medium

- Preparation of the central technical specifications (URS)
- Creation and programming of new washing programs
- Roll-out to 3 plants
- Comprehensive test planning
- Validation of the cleaning processes
- Creation of risk analysis
- Project cost estimates as well as time planning
- Interface coordination


2020

02/2019 - 11/2020

REVAMP & STANDARDIZATION | Inventory clean rooms

Project Type:
Target:
Role:
Budget:
Project Team:
Conversion
Compliance with necessary normative requirements
Project engineer, qualification manager
On request
On request
Complexity: Medium

- Carrying out a GAP analysis taking into account international norms & standards
- Layout planning for the introduction of a uniform lock concept
- Interface coordination
- Management qualification planning
- Close consultation with management
- Employee training


2019

10/2019 - 12/2019

PROCESS OPTIMIZATION I Balloon forming process

Project Type:
Target:
Role:
Budget:
Project Team:
Restructuring
Compliance with necessary normative requirements
Project Engineer
On request
On request
Complexity: Medium -High

- Carrying out GAP analyses taking into account international norms & standards
- Detailed process optimization of a molding process
- Roll-out to 8 molding lines
- Comprehensive test planning
- Time & Budget Planning
- Support planning for the optimization of the associated cleanroom processes
- Interface coordination
- Management of qualification & validation
- Close consultation with the production management
- Employee training


2017

12/2015 - 08/2017

NEW CLEANROOM CONSTRUCTIO | OSD Solids production

Project Type:
Target:
Role:
Budget:
Project Team:
New construction, OSD
Production expansion, growth increase
Project Engineer (Cleanroom & Infrastructure)
On request
On request
Complexity: High

> Project flow Basic Design Phase <
- Planning of material and personnel flows as well as zone layout
- Supporting planning for the infrastructure of process equipment and cleanroom monitoring
- Planning of lock processes and lock equipment as well as interfaces to automation
- Basic coordination to all involved trades (construction & TBE, process, automation)
- Partial responsibility for cleanroom fitting
- Design cost estimates (DCE) of the entire cleanroom area.
- Value engineering and cost savings

> Project flow detail design phase <
- Responsibility for logistical material and personnel flows, adaptation of zone layout
- Overall responsibility for cleanroom fit-out
- Preparation of the bill of quantities and the technical specifications. Specifications for the total clean room expansion
- Supporting plant and 3D planning as well as supporting piping design
- Interface coordination to all involved trades (architecture, TBE / construction etc.)
- Installation of process equipment and GMP-compliant integration in cleanroom construction
- Preparations for the construction of the plant and clean room areas
- Preparations for the qualification of equipment and the clean room
- Support with the detailed planning of the pelletizing plant


2015

08/2015 - 11/2015

PROJECT SUPPORT | OSD Solids Production

Project Type:
Target:
Role:
Budget:
Project Team:
New construction, OSD
Production expansion, growth increase
Project Engineer
On request
On request
Complexity: Low

- Analysis & progress measurements of the project status and progress based on required documents
- Cost and hourly estimates of personnel resources
- Preparation of project documents


2015

08/2015 - 11/2015

REVAMP OF INTERLOCKS | OEB3 Production Area

Project Type:
Target:
Role:
Budget:
Project Team:
Oncology, OSD
Production expansion, growth increase
Supporting project engineer
On request
On request
Complexity: Very high

- Programming the sluice control
- Support in the preparation of drawings and parts lists
- Preparation of GMP-compliant technical documentation
- Project engineer and deputy Project manager on site
- Assistance with metrological planning and installation of walls and ceilings
- Assistance with the assembly of cleanroom ceilings and walls
- On-site interface coordination between. Logistics, QM, Production and Engineering Fa. Baxter


2015

05/2015 - 06/2015

NEW CLEANROOM CONSTRUCTION | GMP AREA | Hospital

Project Type:
Target:
Role:
Budget:
Project Team:
New building, GMP preparation
Production expansion
Supporting project engineer
On request
On request
Complexity: High

- Programming the sluice control
- Support in the preparation of drawings and parts lists
- Preparation of GMP-compliant technical documentation
- Project engineer and deputy Project manager on site
- Assistance with metrological planning and installation of walls and ceilings
- Assistance with the assembly of cleanroom ceilings and walls
- On-site interface coordination between. Logistics, QM, Production and Engineering Fa. Baxter


2014

06/2014 - 08/2014

CLEANROOM SYSTEM CERTIFICATION |
IPA Fraunhofer Stuttgart

Project Type:
Target:
Role:
Budget:
Project Team:
New building, GMP preparation
Production expansion
Working student
n/a
n/a
Complexity: n/a

- System certification in cooperation with IGA Fraunhofer
- Main contact for the evaluation of cleanroom systems according to ISO EN 14644, VDI2083
- Support in the preparation of the overall report


2009

04/2014 - 07/2009

INTRODUCTION OF A DRIVERLESS TRANSPORT SYSTEM | GMP OSD Production Area

Project Type:
Target:
Role:
Budget:
Project Team:
Re-organization, packing
Cost savings
Supporting project engineer
On request
On request
Complexity: Medium

- Statistical preparation of data for the introduction of automated guided vehicles in the GMP production and packaging sector
- Support in the preparation of technical specifications
- Determination of suitable vehicle types (consideration of routes, loads and geometries)
- Definition and specification of fixed docking stations
- Support for the reorganization of the packaging and logistics area
- Support in the creation of a simulation model
- Cooperation in the selection of suppliers
- Support in the comparison of offers

2009

04/2014 - 07/2009

Support planning for GMP production areas

Project Type:
Target:
Role:
Budget:
Project Team:
Conversion
Cost savings, sustainability
Supporting project engineer
n/a
n/a
Complexity: Medium

- Support in various projects, department engineering
- Comprehensive data evaluation and simulation for the introduction of a driverless transport system in final packaging
- Measurement of energy flows to building services and process plants
- Creation of an overall value stream analysis
- Support for the procurement of a pellet plant for the provision of cooling and process energy
- Optimization in the storage of semi-finished goods, support in the reconstruction of storage areas.
- Contact person in specialized topics zw. QM, production and engineering


AT A GLANCE


Completed projects

13

Projects > 0.5 million EUR


Within approx. 10 years in different functions and roles

Project budget

7.5

EUR million Maximum budget


Handling and responsibility over different project budgets

Personnel deployment

20

Persons max.


Personnel deployment planning of small to large project teams

Average project duration

0.75

Years


Average time spent on projects